Project Overview

A plot of land in Midland Acres, near Frank Sound, was to be subdivided and sold. A requirement prior to the subdivision being approved was the availability of potable water. Several lengths of SDR21 4" J/G pipes and fittings were imported to be installed.

Risk and Constraints

One common feature of Midland Acres is the high rock content. It took a considerable number of equipment hours to excavate in rock to reach the minimum depth required for the water main installation.

Strategy & Implementation

We worked closely with the Water Authority to certify the installation as this would become part of the public water system. Strategic planning of excavation work minimized equipment time while meeting all depth requirements.

Achievements

The water main installation was successfully certified by the Water Authority, enabling the subdivision approval to proceed and adding value to the land parcels.

Project Details

Location
Midland Acres, Frank Sound
Year Completed
2023
Total Area
Infrastructure
Duration
3 months

Project Gallery

Midland Acres Water Main - Image 1
Midland Acres Water Main - Image 2
Midland Acres Water Main - Image 3
Midland Acres Water Main - Image 4